Category Archives: Case Studies

Reclad with CCC still had rot and leaks left – new homeowner carrying the can

From the current homeowner (1 September 2008): “My property is a two storey townhouse, the original dwelling built approx 6 years ago, with addition added approx 3 years ago. Was originally plaster clad, and has since been re-clad with weatherboard/plywood. … Continue reading

Posted in Case Studies, Mdu Probe System, Testimonials | 2 Comments

2004 Kelleway Case Study – first WHRS Adjudication

First Adjudication shows distinct “lack of science” during expert investigation and conclusions Understand what is behind reasons for reclad. Arbitrator stated ‘lack of science’ in reaching that award. Weathertightness experts lacked knowledge on what the science was, and got reasons … Continue reading

Posted in Adjudication, Case Studies | Tagged , | Leave a comment

New Homes with Fungally Attacked Timber

These houses are timely reminders of the importance of protecting exposed timber framing during all facets of production and construction until enclosure as well as the importance of treatment chemicals in protecting its structural integrity during this process #839 , … Continue reading

Posted in Case Studies, Mdu Probe System | Tagged , | Leave a comment

7yr Weatherboard-clad house failing

7yr Weatherboard-clad house failing This house is a good example showing that issues in buildings typically called “leaky homes” are not isolated to plaster homes alone. #266

Posted in Case Studies | Tagged | Leave a comment

Reclad still failing

Reclad still failing This is a classic situation showing how it doesn’t pay to blame the cladding first – and think that recladding will solve your woes. This property has been reclad for at least 3 years now – yet … Continue reading

Posted in Case Studies, Design | Tagged | Leave a comment

Damage and leaks in building despite being OK’ed by Surveyor 2 months ago

Damage and leaks in building despite being OK’ed by Surveyor 2 months ago This property was ok’ed by a Building Surveyor during an inspection on behalf of a DBH Determination. The determination concluded the building was Code Compliant. The Council … Continue reading

Posted in Case Studies | Tagged , | Leave a comment

WHRS Ajudication TRI-2008-100-091

WHRS Ajudication WHRS Ajudication TRI-2008-100-091

Posted in Adjudication, Case Studies | Tagged | Leave a comment

2004 Wall Microclimate Analysis (Wall Signature) testing

Auckland City Council were implementing a revised assessment process for older homes applying for CCC. Auckland City Council required an understanding of what is happening behind actual walls and could a leak event be introduced and the wall response measured. … Continue reading

Posted in Case Studies, Project M, Research | Tagged , , | Leave a comment